Highland Council is planning to carry out daytime carriageway resurfacing improvements on the Ardnamurchan Peninsula.
The location of works includes the A861, B8007 and A884.
Resurfacing improvements will start on Monday May 13 for an expected duration of three weeks. All works will be daytime works and no works will take place over the weekend.
Due to the narrow carriageway widths and single carriageway sections of the routes, and to protect the workforce and members of the public, the road requires to be closed with amnesty opening periods.
The table below outlines the location of works, dates and amnesty schedule.
Location of Works |
Duration |
Work Hours |
Traffic Management |
A861 Sallachan Quarry |
Monday 13 May |
09:00 to 17:00hrs |
1hr Road Closure with 30-minute amnesty |
B8007 Salen to Camasinas |
Tuesday 14 May to Thursday 23 May (weekdays only) |
09:00 to 17:00hrs |
2hr Road Closure 30-minute amnesty |
A884 Falls Brae |
Friday 24 May to 30 May (weekdays only) |
09:00 to 17:00hrs |
1hr Road Closure with 30minutes amnesty |
This essential surfacing programme is a significant capital spend which will fix existing carriageway defects and significantly improve road conditions.
Highland Council thanks the public for their patience.
Should you require any further information, or have any queries related to this above work, email the roads team at: Roads.LNBS@highland.gov.uk.
Yes! I would like to be sent emails from West Coast Today
I understand that my personal information will not be shared with any third parties, and will only be used to provide me with useful targeted articles as indicated.
I'm also aware that I can un-subscribe at any point either from each email notification or on My Account screen.